Since giving the venture its go-ahead in 2021, BHP has been injecting capital to hurry up its improvement even when potash costs have been falling. Even earlier than its approval, the group had spent $4.5 billion on the venture.
The proposed potash mine is being in-built 4 levels, with $5.7 billion already spent on the primary stage alone. The purpose, in line with BHP, is to start out Section 1 manufacturing in late 2026, with anticipated potash manufacturing of 4.2 million tonnes a 12 months.
In its quarterly replace Thursday, the Australian mining group additionally stated that the second stage, which was permitted final 12 months and is predicted to value one other $4.9 billion, will begin in 2029. This might add one other 4.4 million tonnes of annual manufacturing.
All the four-phased improvement may have annual manufacturing of between 16-17 million tonnes, BHP beforehand acknowledged.